"Bulgartransgaz" EAD resumes the supply of natural gas to consumers in Sofia and Pernik ahead of schedule

Energy / Bulgaria
3E news
633
article picture alt description

Photo source: Marinela Arabadzhieva / 3eNews

In implementation of the repair program of "Bulgartransgaz" EAD in the period from 08:00 on 08/08/2023 (Tuesday) to 08:00 on 10/08/2023 (Thursday) it was planned to carry out planned repair activities on the gas transmission pipeline from "Gorni Bogrov" linear crane assembly to "Novi Iskar" treatment plant. This was announced by the gas operator today.

Their implementation will ensure maximum security in the transmission of natural gas through the national gas transmission system for the upcoming autumn-winter season.

Thanks to the efforts made by the employees of Bulgartransgaz EAD, the repair was successfully completed earlier than the scheduled deadline. After 15:00 on 09.08.2023, the phased restoration of natural gas transmission will begin at the exit points of the gas transmission network as follows: C051-AGRS "Chepintsi", C054-AGRS "Novi Iskar", C053-AGRS "Sofia" - 2", C055-GRS "Sofia - 3", C056-GRS "Sofia - 4" and C057-GRS "Pernik".

In this way, an opportunity will be provided to restore the consumption of natural gas for "Overgas Networks", "Sofia Heating" and all end users of natural gas in the territory of Sofia and Pernik earlier than the scheduled time.

Tags:

Comments

More from Bulgaria:

Предишна
Следваща